| Aug 8, 2009 |
LSV opening ceremony & celebration |
| June 2009 |
A/C, phone & computer lines < Phase I completed > |
| May 2009 |
Outdoor corridor and sidewalk |
| April 2009 |
Water & electricity installation. |
| March 2009 |
All buildings completed. |
| Feb 2009 |
Flooring, interior & exterior painting. |
| Jan 2009 |
Structural construction for six buildings. |
| Present |
Many building with roofs and walls |
| Oct 2008 |
Building second floor |
| Aug 2008 |
Building foundation of
family unit,
administration,
classroom building,
cafeteria and
auditorium |
| July 2008 |
Electricity pole
installation |
| June 2008 |
Paved road |
| March 2008 |
Concrete fence
completed |
| Jan 2008 |
Foundation for fence |
| Jan 10, 2008 |
Building Permit
Approved |
| March 4, 2006 |
Ground Breaking
|